Pawnee Nation IHS Drive Thru Facility

Healthcare Facility Construction in Pawnee OK

Developed for the Pawnee Nation in partnership with the Indian Health Service (IHS), this ground-up healthcare facility was designed to support mass testing, treatment, and immunization efforts. It stands as a permanent solution to the temporary outdoor operations previously used for public health crises.

This project marked a milestone for Stronghold Construction as our first ground-up build and our first progressive design-build delivery. The facility provides a climate-controlled, professional environment for both healthcare providers and tribal members.

Progressive Design-Build Healthcare Delivery

Project Overview

The Pawnee Nation IHS Drive-Thru facility was built to streamline rapid public health responses. Its design emphasizes vehicle flow, patient safety, and clinical efficiency, allowing for high-volume testing and treatment without compromising care quality.

Stronghold managed every phase of the project, ensuring that the new infrastructure met strict federal compliance standards. The facility serves as a critical asset in the Pawnee Nation’s healthcare portfolio, providing a durable platform for future community health initiatives.

Project Details

IHS Healthcare Testing Infrastructure

Client: Pawnee Nation & Indian Health Service

Location: Pawnee, Oklahoma

Delivery Method: Progressive Design-Build

Project Type: Specialized Healthcare Facility

Building Size: ~2,500 Square Feet

Structure: Ground-up Healthcare Infrastructure

Project Goals

Rapid Public Health
Response Goals

The project was driven by several critical objectives:

01. Replace temporary outdoor tents with a permanent, climate-controlled facility

02. Support high-volume drive-thru testing and immunization efforts

03. Meet all IHS and federal medical documentation requirements

04. Deliver a ground-up facility under a fast-track schedule

Key Challenges

Subcontractor Scarcity

A busy regional market required proactive scheduling to ensure specialized healthcare trades were available.

Federal Compliance

Navigating the rigorous documentation and inspection standards required for IHS-funded medical facilities.

First-Build Milestones

Balancing the complexities of Stronghold's first ground-up project with a progressive design-build model.

Efficiency x Open-Book Pricing

Stronghold executed the project with a focus on cost certainty, utilizing phased work releases and open-book pricing. The result was a facility delivered under budget, with unused contingency funds returned to the Pawnee Nation and a formal recommendation for future IHS work.

Ready to start your next project?

We specialize in solving complex construction challenges through close collaboration.

Previous
Previous

Norman Transit Center

Next
Next

Seminole Nation Pool Annex - Coming Soon