Stronghold Construction turned an empty white-box suite on South Broadway in Edmond into The Back Nine Golf, a 24/7, membership-based indoor golf facility with three Full Swing simulator bays, a dedicated putting area and a lounge.

Working from Green Couch Design's plans, Stronghold built out the complete commercial tenant improvement from late March to late May 2026, ahead of the venue's June 2026 grand opening.

Turf putting green with flag pins at The Back Nine Golf in Edmond, OK

Project Overview

White-Box Tenant Improvement

The space came to Stronghold as a bare white box: open structure overhead, concrete floors and no interior build-out. The finished facility includes three simulator bays sized for full swings, a turf putting area, a lounge, restrooms and support spaces.

Simulator bays leave little room for error. Ceiling heights, screen and projector placement, lighting and bay walls all had to line up so the Full Swing systems could be installed and calibrated in time for opening day.

Full Swing simulator bay with lounge seating at The Back Nine Golf

Project Details

Commercial Tenant Improvement

Client: The Back Nine Golf

Location: Edmond, Oklahoma

Delivery Method: General Contracting

Project Type: Commercial Tenant Improvement / Entertainment

Design: Green Couch Design

Construction: March to May 2026

Grand Opening: June 2026

Bar-height seating along the simulator bays at The Back Nine Golf

Project Goals

Premium Experience
on a Fast Track

The project was driven by several critical objectives:

01. Convert a bare white-box suite into a finished golf facility

02. Build three simulator bays ready for Full Swing systems

03. Add a putting area and lounge for members and guests

04. Coordinate inspections to keep the opening date on track

05. Deliver a finished space ready for 24/7 member access

Key Challenges

Compressed Schedule

The full build-out ran from late March to late May 2026 so the owners could open their doors in June.

Simulator Bay Tolerances

Screens, projectors, lighting and bay walls had to be positioned precisely for the simulators to perform as designed.

Open-Structure Ceilings

With the structure left exposed overhead, ductwork, conduit and lighting stayed visible, so routing and finish quality mattered as much as function.

Golf ball beside the cup on the putting green at The Back Nine Golf
Stronghold Construction icon

Speed x Precision

From empty suite to finished golf facility in about eight weeks, The Back Nine shows how Stronghold handles fast-track tenant improvements: tight coordination with the designer, early planning for specialty equipment and a schedule built around the owner's opening day.

Ready to start your next project?

We specialize in solving complex construction challenges through close collaboration.

Previous
Previous

Barking Waters Head Start

Next
Next

Mekusukey Mission Water & Wastewater