Pawnee Nation Solar Farm

Solar Farm Construction in Pawnee OK

Stronghold Construction is the design-builder for the Pawnee Nation of Oklahoma's solar farm, funded through the USDA Rural Energy Pilot Program (REPP). The project pairs ground-mounted solar arrays with battery storage and EV charging to move the Nation toward greater energy independence.

Working with Green Couch Design as design lead, Stronghold has carried the project from preconstruction and design through procurement and construction under a design-build agreement with a guaranteed maximum price.

Ground screw foundations installed for a Pawnee Nation solar array

Project Overview

Renewable Energy Design-Build

The solar farm is built on Nation land in Pawnee, with ground-mounted arrays set on ground screw foundations over a graded, gravel-surfaced site. During construction the Nation expanded the scope, adding a fourth array and lengthening an existing one.

Beyond the arrays, the project adds battery energy storage at two Nation facilities, an EV charging station at Stone Wolf Casino, and a new utility interconnection with Indian Electric Cooperative. The program also funded solar workforce training for Pawnee Nation members, delivered with OSU-OKC and Everblue.

Pallets of solar modules staged for the Pawnee Nation solar farm

Project Details

Design-Build Renewable Energy

Client: Pawnee Nation of Oklahoma

Location: Pawnee, Oklahoma

Delivery Method: Design-Build (GMP)

Program: USDA Rural Energy Pilot Program (REPP)

Project Type: Ground-Mount Solar, Battery Storage & EV Charging

Design Lead: Green Couch Design

Status: Under Construction

Target Completion: December 31, 2026

Racking pipe delivered for the Pawnee Nation solar project

Project Goals

Energy Independence
for the Nation

The project is driven by several critical objectives:

01. Deliver ground-mounted solar generation for Pawnee Nation facilities

02. Add battery storage to support key Nation buildings

03. Install EV charging at Stone Wolf Casino

04. Interconnect safely with the local electric cooperative

05. Train Pawnee Nation members for careers in solar installation

Key Challenges

Owner-Furnished Materials

Solar modules and racking were purchased directly by the Nation, so Stronghold coordinated delivery, staging and storage of owner-furnished material alongside subcontracted installation.

Scope Growth Mid-Project

The Nation added a fourth array during construction. Stronghold priced and integrated the expansion without stopping work on the original arrays.

Funding Timeline

The program's funding timeline compressed site preparation, foundation installation and utility interconnection into a late-fall and winter schedule.

Ground screw installation at the Pawnee Nation solar farm
Stronghold Construction icon

Design-Build x Workforce

The Pawnee Nation Solar Farm shows what design-build can do for a tribal energy program: one team accountable for design, cost and construction, and a training program that builds solar skills within the Nation. Construction is underway, with substantial completion targeted for December 31, 2026.

Ready to start your next project?

We specialize in solving complex construction challenges through close collaboration.

Previous
Previous

Mekusukey Mission Water & Wastewater

Next
Next

Seminole Nation Roads & Trails Program